Lekki Deep seaport to commence operation 2022- Amaechi

L-R: The Minister of Transportation, Rotimi Amaechi, Permanent Secretary, Federal Ministry of Transportation, Dr. Magdalene Ajani, Acting Managing Director, Nigerian Ports Authority (NPA), Mohammed Bello Koko, and Chairman Lekki Port, Abiodun Dabiri during Port facility appreciation tour of Lekki Port in Lagos.

The Minister of Transportation, Rotimi Amaechi, has urged the promoter of the Lekki Deep Seaport, Lekki Port LFTZ Enterprise Limited, to fast track construction work and see to it that the Port commences operation by 2022.

Amaechi, who stated this during an inspection of the Port by the Federal Ministry of Transportation and other government agencies including the Nigerian Ports Authority (NPA), the Nigerian Shippers’ Council (NSC) and the Nigerian Maritime Administrative and Safety Agency (NIMASA), expressed satisfaction over the level of progress recorded on the construction of the Lekki Deep Sea Port project.

He said, “I am very delighted and impressed with the pace and the progress of construction work on this project from the last time I was here in November 2020.

“The promoter of the project – Lekki Port LFTZ Enterprise Limited has demonstrated strong commitment and capacity to deliver the project as agreed.”

The Minister urged the management of the seaport and other stakeholders to work tirelessly to ensure that the Port becomes operational by mid 2022.

The Chairman, Lekki Port LFTZ Enterprise Limited, Mr. Abiodun Dabiri, while briefing the Minister on the status of construction of the Port, disclosed that the entire construction is now at 55.4 percent completion.

 

Giving a further breakdown of the status of the components, Dabiri noted that dredging and reclamation has reached 61.11%, Quay Wall 50.39%, Breakwater 67.49% while the landside infrastructure development has reached 33.70% completion.

Dabiri stated that the project is on course and going according to schedule, assuring that at the end of third quarter in 2022, construction work would be complete while commercial operations will commence by fourth quarter (Q4) 2022 as planned.

The Chairman commended Minister for providing the necessary support that has assisted the company to deliver on the mandate for the project and stressed that when completed, Lekki Port would be a world-class Port operating with best-in-class equipment to ensure seamless operations and would comply with global environmental protection standard.

He added that the Port has the deepest seaport in the sub-Saharan African region and would serve as transhipment hub for the region.

Also speaking during the visit, the Acting Managing Director, Nigerian Ports Authority (NPA), Mohammed Bello-Koko assured that the Nigerian Port Authority is ready to play its part to ensure smooth take-off of port operations upon completion of construction. He disclosed that NPA has commenced the process of acquiring all necessary marine equipment, including tug boats and mooring boats.

The delegation that accompanied the Minister on the inspection visit included the Permanent Secretary, Federal Ministry of Transportation (FMoT), Dr. Magdalene Ajani, Executive Secretary, Nigerian Shipper’s Council, Mr Emmanuel Jime and the Director General of the Nigerian Maritime Administrative and Safety Agency, Dr Bashir Jamoh.

 

 